By CroquetClaude · 5 min read · First added 19 Nov 2026
Planning a Renovation Closure
Close once in spring or early summer, tell members early, agree the job in writing, and reopen to social play first.

Close once, in spring or early summer, two courts at a time if you can. Tell members early, agree the job in writing, and reopen to social play first.
Planning a renovation means settling the dates, looking after members, finding the money and agreeing the job with a contractor. For the steps of the work itself, read our main guide, Renovating Your Courts, which explains what each step does to the grass.
Pick the time of year
Queensland courts are couch grass, which grows fastest in late spring and early summer. That is when it recovers fastest. Most Queensland clubs in our records renovate in one spring or early-summer closure, some time between mid-September and January. Some stage it two courts at a time, and some run later into summer or autumn.
Wait until the grass is growing strongly, has been mown a few times, and warm weather is forecast (Lawn Solutions Australia). In South-East Queensland, October to November suits the heavy scarify. Never scarify in winter, when the grass is resting, or in mid-summer heat. Levelling and drainage work can be done in June and July.
Aim to finish before the wet season peaks. Rain helps the grass but delays work. Eildon planned to start its 2023 job on 27 November, "with a (hopefully) wet season almost upon us". Toombul's top-dressing was held up by December rain and finished on 16 January 2025. Plan around Melbourne Cup Day and Christmas too. We hold no source on the best timing in North Queensland.
How long to close
Bribie closed for two weeks in 2024 and planned about 10 days for its contractor in 2025. Eildon planned four weeks for its full contractor job in 2026, recovery included.
| Club | Year | Closed |
|---|---|---|
| Bribie Island | 2024 | 2 weeks, reopened 30 October |
| Bribie Island | 2025 | about 10 days planned, 6 to 16 October |
| Eildon | 2026 | 4 weeks planned, 21 September to 19 October |
| Stephens | 2021 | about 3 weeks for courts 1 and 2; 3 or 4 weeks forecast for courts 3 and 4 |
| Windsor | 2022-23 | about 8 weeks from first scarify to reopening, after floods |
Two courts at a time
Doing half the courts at once keeps play going. Stephens scarified courts 1 and 2 on 1 February 2021, then courts 3 and 4 on 19 February, about three weeks later. Wynnum ran a roster for morning or afternoon play on the courts left open. Caloundra rebuilt its courts two at a time in 2022 and 2023, starting with the bottom two.
Keep members playing
Ask neighbour clubs for help. In 2026 Toombul and Windsor welcomed Eildon players: Toombul at its Wednesday and Saturday morning social days, and Windsor on Wednesday and Saturday afternoons. During Bribie's 2024 closure, its members played at Caloundra and Eildon. Eildon also kept its mahjong going and did a spring clean.
Tell members early
Eildon's notice ran seven weeks ahead. It gave the dates, who would care for the lawns, the reopening event, and said "All activities that do not involve playing on the lawns will continue as usual."
Tell members the courts will look bare, brown, torn up and sandy, and will play slowly at first. Say where they can play meanwhile. Then reopen with an event: Eildon held a Melbourne Cup lunch in 2025; Bribie held a BBQ and a Gala Day.
Look for a grant or council support
Ask your council. Eildon thanked the City of Moreton Bay, "who generously granted us funds". The works at The Range Maleny "had support from Sunshine Coast Council"; its story does not say what kind. No amounts were published.
Agree the job in writing
To find suppliers, try the directory at Turf Queensland. Then agree these nine things in writing:
- Scope and order: which steps, which courts, which dates.
- Levelling standard: what "finished" means and how it is measured. Write it down. See Top-dressing and levelling.
- Sand: what kind, how much, who orders it, and when it arrives.
- Clean-up: who removes the thatch and cores, and where they go.
- Machines and operators: experienced people, blades set correctly.
- Weather: what happens when rain stops work.
- A check before they leave: a straightedge walk with your greenkeeper, and a written list of anything left to do.
- Aftercare: who fertilises, waters and mows. At Eildon in 2026, the club's greenkeeper, Rino, was to oversee this.
- Insurance, price and payment: public liability, the price, and payment after the walk-over.
If volunteers will run hired machines, ask your insurer first.
Recovery week by week
This is a rough guide only. Your greenkeeper's advice comes first.
| Week | What members see | What the club does |
|---|---|---|
| 1 | Bare, sandy, torn up | Water fertiliser in; keep people off; water mornings |
| 2 | First green shoots | Keep watering; brush sand in; check levels |
| 3 to 4 | Patchy green | First light mow, set high; roll once settled |
| 4 to 6 | Mostly covered, soft and slow | Lower the cut in steps; decide on reopening |
Start mowing at about 15 to 20mm and come down over three or four mows. Never mow wet grass.
Slow courts are normal
When Caloundra's newly upgraded courts came back in early 2023, its association players found them "very slow". Wynnum warned "The speed of the courts will take a bit of getting used to." The surface firms up over the following weeks.
Deciding to reopen
The committee decides, on the greenkeeper's advice. Check that grass cover is nearly complete, the surface feels firm, the straightedge shows no new dips, and a ball rolls true. Settled courts can open first. Start with social play and keep tournaments for a few weeks later. Then read Lawn Care Through the Queensland Wet Season.